To ask the Minister of State, Department for Transport what estimate has been made of the cost to the public purse of the completion of the works in the South East required as a consequence of the improvement notice service on Network Rail. [324702]

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

The Office of Rail Regulation served an improvement notice on Network Rail Infrastructure Ltd. on 18 March requiring the company to comply with its own standards for inspecting structures to ensure safety. Network Rail is already fully funded to meet the requirements of health and safety law.