Olympic Games 2012: Construction

Volume 508: debated on Thursday 8 April 2010

To ask the Minister for the Olympics what the cost was of building the freight facility at the main Olympic site. (323339)

The Olympic Delivery Authority (ODA) has constructed a temporary wharf on the Waterworks River for the construction phase of the programme to provide contractors with the opportunity to move material into and out of the Park by water. The construction cost of this is £1.86 million (excluding VAT), This figure includes the costs of the pontoons, moorings, pilings, hard-standing, vehicle access and river wall protection.