Rail Electrification

Volume 524: debated on Thursday 10 March 2011

The Government’s policy is to support the progressive electrification of the railway. The Department for Transport will continue to consider the business case for the scheme that my hon. Friend mentions as part of the work to inform decisions in the next railway control period, beginning in 2014.

Does the Secretary of State agree that there would be huge benefits to the east midlands from the electrification of the line? Given the massive economic and housing growth predicted for the east midlands over the next few years, an early timetable for electrification of the line would be very helpful to business and planners.

My hon. Friend is right to note that there is a strong case, on the face of it, for the electrification of the midland main line. He will know that there are works currently under way on the line to improve line speeds, and I had the opportunity to view them from the cab of an East Midlands Trains service on Monday. When they are completed at the end of 2013, they will result in the journey time from London to Sheffield being reduced to less than two hours.

Does the Secretary of State accept that in the last assessment, the business case for the electrification of the midland main line was just as strong as that for the Great Western line? As he is not prepared at this stage to commit to the electrification of the line in one go, will he re-examine the possibility of introducing the new bi-modal trains on the line? On that basis there could be incremental electrification without the up-front costs coming all at once.

I understand the hon. Gentleman’s question, and I am aware of the proposal that East Midlands Trains is examining to introduce bi-modal running on the line. The difference between the midland main line and the Great Western main line is that the midland main line’s future function will be affected by the decision on High Speed 2. It is right that we consider the matter as one for the next control period, in the full light of the decision on HS2 that will be taken later this year.

12. What recent representations he has received on the electrification of rail lines between Cardiff and Swansea and west of Swansea. (45285)

I have received representations calling for electrification of the Great Western main line to be extended as far west as Swansea. We have looked carefully at the arguments but I regret to tell the hon. Gentleman that there is not, at present, a viable business case for electrification of the main line between Cardiff and Swansea. I have given the House an undertaking that I and my right hon. Friend the Secretary of State for Wales will keep the matter under review.

I regret to inform the Secretary of State that last week’s announcement went down like a lead balloon in the communities in west Wales that I represent. Later in the week, the Business Secretary made a speech saying that investment in high-speed rail and electrification was an example of how the UK Government were going to rebalance the economy. Is the message therefore that as far as the UK Government are concerned, the Welsh economy stops at Cardiff?

No, I will tell the hon. Gentleman what the message is. It is that my announcement last week will result in the journey time to Swansea being cut by 20 minutes, to two hours and 39 minutes, delivering to people in Swansea all the time-saving benefits that would be delivered were electrification to progress as far as Swansea. I am sorry to have to tell him this, but if he looks at the facts of the case, the costs to the taxpayer and the benefits to the people of Swansea, he will discover that at the present time our decision is the right one. As I have said, we will keep it under review.

I am sorry to return to this subject, but will my right hon. Friend tell the House what feasibility studies have been undertaken on how long the Severn rail tunnel will be closed when the electrification project is under way? Would alternative diversion routes, such as the Kemble to Swindon rail scheme, be useful additions when the scheme is constructed?

My hon. Friend is extremely diligent in pursuing the Swindon to Kemble rail scheme. Our proposals will require electrification through the Severn tunnel. I have not yet received a detailed proposal from Network Rail on how engineering work will be carried out, but we will be mindful of the potential for disruption.

I shall not express my disappointment with the decision again, but I would like to know this: are you going to publish the information on how you reached the financial decision? People in Swansea ought to be told what that decision was based on.

If the hon. Lady would like to see the business case analysis for electrification from Cardiff to Swansea, I am happy to make it available to her. I can tell her that it will not reinforce her case.