4. What estimate he has made of the potential cost of transport infrastructure for a third runway at Heathrow. (904740)
The Airports Commission assessed the surface access requirements of each short-listed airport proposal as part of its work published in July 2015, and it estimated that there would be a cost of up to £5 billion for surface access works in relation to the Heathrow north-west runway.
There are clearly widely differing estimates of the capital costs of building an additional runway at Heathrow, but what is not in dispute is that building an additional runway there will cost significantly more than building one at Gatwick. If the Government decide to go ahead with expanding Heathrow, who will pay the difference—the airline passenger or the taxpayer?
The hon. Lady is absolutely right that some of the estimates for surface access differ widely, even by the standards of some economists. One must bear in mind that the three sets of figures include different things over different timescales, the main ones being the work required exclusively for airport capacity, where the airport would be expected to make a major contribution; the projects that support airport capacity, but have wider benefits; and those in the Transport for London figures, which are needed in respect of wider population and economic growth during the next 20 to 30 years.
Do the Government accept the Airport Commission figure, which is £5 billion, the £2 billion from Heathrow or the £18 billion from TfL? Is this not just more of the 30 years of disinformation we have had out of Heathrow? When are the Government going to come to a decision, make their view clear and stop delaying matters just because of elections?
If the hon. Gentleman had been paying attention to what I just said, he would know that I explained that those figures relate to different things over different timescales. On the decision, perhaps he could wait until my hon. Friend the Member for Twickenham (Dr Mathias) poses her question to the Secretary of State.
Can the Government give us any indication of the time period for construction from when the decision has been taken until the runway at either Gatwick or Heathrow is completed?
It is important to note that the additional time we are taking to look at a number of economic and environmental factors will not delay the delivery of a runway at whatever location is decided on.