Manston Airport: Reopening and Development
20 May 2020
Volume 676
The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

I have been asked by my right hon. Friend, the Secretary of State (Grant Shapps, MP), to make this written statement. This statement concerns the application of 17 July 2018 made by RiverOak Strategic Partners Ltd (“the Applicant”) under the Planning Act 2008 for the proposed reopening and development of Manston Airport in Kent.

Under sub-section 107(1) of the Planning Act 2008, the Secretary of State must make his decision within three months of receipt of the examining authority’s report unless exercising the power under sub-section 107(3) to extend the deadline and make a statement to the House of Parliament announcing the new deadline.

The Secretary of State received the examining authority’s report on the Manston Airport development consent order application on 18 October 2019 and, following an earlier extension of four months, the current deadline for a decision is 18 May 2020.

The deadline for the decision is now to be extended to 10 July 2020 to enable further work to be carried out before determination of the application.

The decision to set a new deadline is without prejudice to the decision on whether to grant development consent.

[HCWS247]