British Library: Project Plans And Cost

Volume 495: debated on Thursday 31 March 1988

The text on this page has been created from Hansard archive content, it may contain typographical errors.

asked Her Majesty's Government:What their plans are for the completion of the National Library at Euston; and what money will be lost or saved by postponement of work on this site.

Work is currently in progress on the construction of Stage 1 A of the new British Library, and this is expected to be completed by 1993. A feasibility study is currently being carried out by the Property Services Agency to draw up a plan for completing the project which will meet the key requirements of the library at the minimum additional cost. When the study is complete, and this is expected to be in mid-1988, the options will be examined and a decision will be made.