Thameslink Upgrades

The following is an extract from the Minister’s reply to the Adjournment debate on 18 April 2018.

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

First, when was the decision made to make changes to East Midlands trains that would impact Harpenden? At what stage were changes to Harpenden’s services considered and decided upon?

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

This has been one of the biggest timetabling changes the system has ever undertaken and, as I have said, it will not have satisfied everybody in its first iteration. However, December is coming along in not too lengthy a period of time, and hon. Members are always welcome to put suggestions to the Department and to their operators for consideration.

The impact of the midland main line works only became apparent to us in November 2017, as I mentioned. This short timeline meant that a specific consultation for Harpenden passengers was simply not a viable option.

[Official Report, 18 April 2018, Vol. 639, c. 437.]

Letter of correction from Joseph Johnson:

An error has been identified in the response I gave to the hon. Member for Hitchin and Harpenden (Bim Afolami) during his Adjournment debate on Thameslink Upgrades.

The correct response should have been:

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

This has been one of the biggest timetabling changes the system has ever undertaken and, as I have said, it will not have satisfied everybody in its first iteration. However, December is coming along in not too lengthy a period of time, and hon. Members are always welcome to put suggestions to the Department and to their operators for consideration.

The impact of the midland main line constraints only became apparent to us in November 2017, as I mentioned. This short timeline meant that a specific consultation for Harpenden passengers was simply not a viable option.