Fire Service

Volume 457: debated on Thursday 22 February 2007

To ask the Secretary of State for Communities and Local Government what the estimated cost is of each regional fire control centre; and what stage each regional project has reached. (117584)

Good progress is being made on the project at regional level. Three regions have already established their local authority controlled companies that will operate their Regional Control Centre. One Regional Control Centre Director is in post and the recruitment of others is in hand. Regions have completed preliminary planning and scoping work around all the major activities they will need to undertake to transfer controls to the RCC network.

Detailed planning will start in the next few months once the IT contract has been awarded and the timetable for transfer to the new system has been agreed.

Each Regional Control Centre will be leased from the owners of the buildings. Details of the rents, lengths of leases and the dates when the buildings are due for completion are set out in the following table.

Region

Lease length (years)

Rent (£ per annum exclusive of VAT)

Target practical completion date

Rent commencement date

North East

20

1,156,009

30 March 2007

13 January 2008

East Midlands

25

1,205,000

29 June 2007

20 January 2008

South West

20

1,213,500

16 May 2007

16 November 2007

West Midlands

25

1,358,311

20 December 2007

4 October 2008

North West

25

1,197,500

1 July 2008

1 January 2009

Yorkshire and Humberside

20

1,198,808

1 July 2008

14 April 2009

East of England

25

1,349,322

1 October 2008

21 April 2009

South East

25

1,445,000

14 May 2008

14 November 2008

London (estimate only)

—

—

Q1 2010

—

A public procurement process under EU rules is still under way for the London regional control centre