To ask the Secretary of State for Children, Schools and Families how many private finance schemes have been signed under the Building Schools for the Future programme; and what the (a) contractor and (b) length of contract is in each case. (187166)

There are currently 13 signed PFI deals as a result of the BSF programme. Details regarding the contractor and the contract length are included in the following table:

LA PFI scheme

Contractor

Contract length (years)

Bradford

Integrated Bradford

25

Bristol

Skanska Education Partnerships

25

Lancashire phase 1

Catalyst Land Lease

25

Lancashire phase 2

Catalyst Land Lease

25

Leeds phase 1

Environments for Learning (E4L)

25

Newcastle phase 1

Aura

25

Solihull

BAM PPP

25

Waltham Forest

Bouygues Partnership for Education and the Community

25

South Tyneside and Gateshead phase 1

Inspired Spaces

25

Leicester City phase 1

Miller Consortium

25

Knowsley

Transform Schools

25

Lewisham phase 1

Learning 21

25

Sheffield

Paradigm

25