The average time taken to provide an initial response to completed wind energy pre-planning consultation pro forma, in each of the past five years is:
Response time (days) Number of pre-planning applications 2003 156 913 2004 165 714 2005 110 738 2006 95 806 2007 70 906 1 Note: The figures for 2003 and 2004 are estimates based on the paper records kept at that time.
Although we have no formal target, we aim to provide an initial response within 56 days. This aspiration was based on the response times in 2003-04, but the complexity of applications since then has meant that the response time has regrettably been longer than we wish. We have, however, reduced the time taken in each of the last two years and aim to further reduce the time taken in future years.
Many meetings take place with wind farm stakeholders covering numerous issues, including radar clutter. The Ministry of Defence has a number of concerns with turbines over and above effects on radar; for example, low flying and seismometers. Moreover, wind turbines have a number of effects on radar of which clutter is only one.
The information requested is therefore not held centrally and could be provided only at disproportionate cost.
This information is not held centrally and could be provided only at disproportionate cost.
At the pre-planning stage, Defence Estates does not reject applications, but makes developers aware of concerns which the Ministry of Defence would wish addressed before a formal planning application is submitted. In each of the past three years, the number of wind energy pre-planning consultations received by Defence Estates with which it raised concerns is:
Number of wind energy pre-planning consultations to which the MOD raised concerns Percentage of total wind energy pre-planning consultations received by MOD 2005 303 41 2006 387 48 2007 251 28
These figures include both offshore and onshore applications.
The Ministry of Defence (MOD) is always willing to do what is practicable to engage with developers and their consultants to address concerns with proposed wind turbines.
In some cases a meeting will be appropriate to discuss issues, including any mitigation being proposed. In such instances the MOD personnel participating in those meetings will be decided according to the requirements of the case to be discussed.
However, the Department has held no meetings, with either wind farm developers or wind farm consultants, with the specific purpose of considering whether to allow MOD personnel from affected sites to discuss with developers technical issues for those sites. Neither has the MOD declined requests for such meetings.
The total numbers of onshore wind energy pre-planning consultations received by the MOD with which the MOD raised concerns in each of the past three years are:
Number of onshore wind energy preplanning consultations to which the MOD raised concerns Percentage of total wind energy preplanning consultations received by MOD 2005 302 41 2006 386 48 2007 250 28
In each of the last three years, the number of onshore wind energy planning applications to which this Department objected is:
Total number of planning applications received Number of onshore wind energy planning applications to which the MOD objected Percentage of total number of objections raised to wind energy planning applications 2005 74 10 13 2006 78 12 15 2007 70 9 13
Records show that on only one occasion was a Ministry of Defence (MOD) objection lodged after the application was considered by the appropriate consenting authority. In that case planning permission had been refused and the developer lodged an appeal. The planning Inspectorate granted the MOD permission to participate in the inquiry, which has been postponed to allow further discussion regarding the MOD's objections.
There has been no occasion on which the Ministry of Defence objected to a planning application for an onshore wind farm development during a public inquiry after previously not raising an objection.