Building Schools for the Future Programme
29 March 2010
Volume 508
The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

To ask the Secretary of State for Children, Schools and Families what estimate he has made of the total cost to each local education partnership of all completed Building Schools for the Future projects. [322854]

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

[holding answer 18 March 2010]: Information about the total cost to each local education partnership of all completed major building projects within the Building Schools for the Future programme is set out in the following table. The information has been provided for those projects where actual costs are available. Estimated figures have not been provided for those projects where figures have not been validated.

Local authority

School

Total project cost (£)

Bradford

Titus Salt School

26,082,591

Bradford

Tong High School

30,045,100

Bradford

Buttershaw Business and Enterprise College

28,272,307

Bristol

Bristol Brunei Academy

24,908,803

Bristol

Brislington Enterprise College

32,517,689

Bristol

Bristol Metropolitan College

24,748,262

Bristol

The Bridge Learning Campus

1

Durham

Durham Johnston

1

Hackney

Stoke Newington School (Phase 1)

1

Hackney

Clapton Girls Technology College

1

Haringey

John Loughborough

4,374,308

Haringey

Highgate Wood Secondary School

4,901,300

Haringey

Alexandra Park School

3,767,500

Haringey

Gladesmore Community School

11,000,100

Haringey

Hornsey School for Girls

4,884,500

Haringey

Park View Academy

12,818,100

Haringey

Northumberland Park Community School

16,548,600

Islington

Holloway School

1

Islington

Highbury Grove + New Sixth Form

29,682,442

Islington

Samuel Rhodes SEN School

7,801,212

Kent

Dane Court School

20,257,678

Kent

The Community College Whitstable

15,709,175

Kent

Northfleet School for Girls (phase 1)

16,896,846

Kent

St. George's Church of England Foundation School (phase 1)

21,632,574

Knowsley

All Saints Centre for Learning

22,717,419

Knowsley

St. Edmunds Arrowsmith Centre for Learning

22,756,312

Knowsley

Huyton Arts and Sports Centre for Learning

24,270,537

Knowsley

Knowsley Park Centre for Learning - serving Prescot, Whitson and the wider community

22,554,109

Knowsley

Kirkby Sports College

23,318,863

Knowsley

Christ the King Catholic and Church of England Centre for Learning

21,544,188

Knowsley

Halewood Centre for Learning

25,907,121

Lambeth

Stockwell Park

27,405,971

Lambeth

Elm Court Special School

8,594,996

Lambeth

Park Campus

6,453,801

Lambeth

The Michael Tippett School

7,314,003

Lambeth

Elmgreen School (temporary accommodation)

25,019,726

Lancashire

Sir John Thursby Community College

33,520,972

Lancashire

Burnley Campus (Thomas Whitham Sixth Form)

31,443,101

Lancashire

Pendle Vale Campus

29,110,960

Lancashire

Shuttleworth College

18,086,760

Leeds

Swallow Hill Community College

30,082,904

Leeds

Allerton Grange

28,010,373

Leeds

Cockburn College of Arts

1

Leeds

Allerton High School

23,473,509

Leeds

Pudsey Grangefield School

21,992,309

Leeds

Rodillian School

27,854,391

Leeds

Temple Moor High School

1

Leeds

Crawshaw

1

Leicester

Soar Valley College

20,870,870

Leicester

Judgemeadow Community College

15,977,428

Leicester

Beaumont Leys

14,098,418

Leicester

Fullhurst Community College

11,887,293

Lewisham

Catford

19,891,414

Lewisham

Sedgehill

36,978,754

Liverpool

Lower Lee SEN School

1

Manchester

Enterprise Academy

1

Manchester

Health Academy

1

Manchester

Our Lady's RC Sports College (Higher Blackley Education Village)

1

Manchester

St. Matthews RC High School

1

Manchester

Newall Green High School

15,750,974

Manchester

Gorton Education Village

21,972,628

Manchester

St. Paul's and Piper Hill

22,707,211

Manchester

Gorton Education Village (Melland High School)

1

Manchester

Meade Hill (Part of Higher Blackley Education Village)

1

Manchester

Buglawton Hall

1

Newcastle

Kenton School

34,182,913

Newcastle

Benfield School (phase 1 of refurb)

11,950,826

Newcastle

Walbottle Campus Technology College

34,892,016

Newcastle

Thomas Bewick (Previous PFI delivered by LEP)

9,342,697

Newham

Brampton Manor School

8,499,260

Nottingham

Big Wood

19,204,412

Nottingham

Hadden Park High School (phase 1)

11,975,940

Sheffield

Yewlands Technology College (two phases)

19,010,769

Sheffield

Talbot Special School

12,032,641

Sheffield

Newfield Secondary School

24,665,265

Sheffield

Silverdale Secondary School

27,034,073

Solihull

Archbishop Grimshaw Catholic School

22,313,974

Solihull

Smith's Wood

23,941,041

Solihull

Park Hall School

22,288,417

Solihull

Lanchester School

8,637,217

South Tyneside

Mortimer Community College

10,165,175

South Tyneside

Jarrow School

17,513,966

Sunderland

Red House Academy

1

Sunderland

Castle View Enterprise Academy

1

Sunderland

Academy 360

1

Sunderland

Washington School

1

Waltham Forest

Walthamstow School for Girls

18,231,000

Waltham Forest

Frederick Bremer

20,061,000

Waltham Forest

Kelmscott School

11,115,000

Westminster

Westminster City Boys

14,818,603

Westminster

St. Marylebone CE

17,155,000

Westminster

Pimlico

33,286,000

1 Total project cost awaiting validation

The total project cost includes all elements that go into the construction of a school building. This includes: the cost of the building; the fixed and loose furniture and equipment; cost incurred to the building beyond the designer's control; external works; contractor's preliminaries; professional fees; overheads and profit; inflation during the construction period; and contingencies.

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

To ask the Secretary of State for Children, Schools and Families what guidance his Department has issued to local authorities on the geographical location of subcontractors tendering for work under the Building Schools for the Future programme. [324081]

The edit just sent has not been saved. The following error was returned:
This content has already been edited and is awaiting review.

The Department has issued no guidance to local authorities on the geographical location of subcontractors tendering for work under the Building Schools for the Future (BSF) programme. It is for each local authority in the BSF programme to determine its own approach to the use of local contractors bearing in mind local employment initiatives and ensuring that that the local authority acts in compliance with its obligations under procurement law.